Process Flow Chart of Industrial Engineering (IE)

By | August 31, 2015

Process Flow Chart of Industrial Engineering (IE)

Mayedul Islam
Merchandiser at Fashion Xpress Buying House.
Badda, Dhaka, Bangladesh.
Email: [email protected]

 

Introduction:

At present Industrial Engineering (IE) is one of the important department for each garments or textile factory. Today’s maximum factory is run by industrial engineers, where they have to follow a process flow chart. By which they can easily control the whole garments production processes. Such kinds of process flow chart has discussed in this article.

industrial engineering

IE dept. in garment industry

Process Flow Chart of Industrial Engineering (IE):

Negotiation with garments merchandiser

Garments analysis

Make P.P meeting if all the required fabrics, trimmings and accessories are in housed

Production target

Set machine layout

Line setting

Line balancing

Continuous production meeting

Collecting production data

Preparing production report

Production report analysis

Report submit to factory manager

All the above processes are discussed in the below table:

SL No.
Process
Procedure
01
Negotiation with garments merchandiser
It is the very first work of an industrial engineer. Here, he should vastly discussed with garments merchandiser about the in-coming garments product.
02
Garments analysis
Confirmed garments product is clearly analyzed here by industrial engineer. It helps to complete rest of the processes very easily.
03
Make P.P meeting
Here, P.P meeting should be organized if all the required fabrics, trimmings and accessories are in housed and take all the pre-cautions for the up-coming garments production.
04
Production target
Production target should set here according to factory capacity. It helps to respect the shipment date.
05
Set machine layout
Machine layout is set here according to total processes needed to complete a garment item.
06
Line setting
In this process, actual line setting should be done to utilize the garment workers properly. If it takes more time in line setting then garments production will be decreased.
07
Line balancing
To minimize the number of work stations, cycle time, line balancing is done here. Its a very important process to achieve desired production target.
08
Continuous production meeting
Production meeting should be done here at regular interval. If any problem will arise during garments production, should take necessary actions to solve that.
09
Collecting production data
Production data should be collected here for preparing production report.
10
Preparing production report
Here, total garments production report has prepared to analysis about the whole production.
11
Production report analysis
Garments production report is analyzed here from different points of view.
12
Report submit to factory manager
Finally garments production report have to submit into the factory manager.